№ роб. | Взаємозв'язок робіт | Шифр роботи | очікувана тривалість, тиж. | ||
попередня | наступна | по подіях | WBS | ||
1 | - | 2,3 | 1-2 | 2П1.1 | 11 |
2 | 1 | 4 | 2-4 | 2П1.2 | 8 |
3 | 1 | 4 | 2-3 | 2П1.3 | 5 |
4 | 2,3 | 5 | 4-5 | 2П1.4 | 2 |
5 | 4 | 6 | 5-6 | 2П1.5 | 18 |
6 | 5 | 7 | 6-7 | 2П1.6 | 2 |
7 | 6 | 8 | 7-8 | 2П1.7 | 2 |
8 | 7 | 9,15,21 | 8-9 | 2П1.8 | 3 |
9 | 8 | 10 | 9-10 | 2. П.2.1.1 | 5 |
10 | 9 | 11 | 10-11 | 2. П.2.1.2 | 13 |
11 | 10 | 12 | 11-12 | 2. П.2.1.3 | 2 |
12 | 11 | 13 | 12-13 | 2. П.2.1.4 | 2 |
13 | 12 | 14 | 13-14 | 2. П.2.1.5 | 3 |
14 | 13 | 27 | 14-25 | 2. П.2.1.6 | 2 |
15 | 8 | 16 | 9-15 | 2. П.2.2.1 | 10 |
16 | 15 | 17 | 15-16 | 2. П.2.2.2 | 27 |
17 | 16 | 18 | 16-17 | 2. П.2.2.3 | 4 |
18 | 17 | 19 | 17-18 | 2. П.2.2.4 | 4 |
19 | 18 | 20 | 18-19 | 2. П.2.2.5 | 5 |
20 | 19 | 27 | 19-25 | 2. П.2.2.6 | 5 |
21 | 8 | 22 | 9-20 | 2. П.2.3.1 | 3 |
22 | 21 | 23 | 20-21 | 2. П.2.3.2 | 6 |
23 | 22 | 24 | 21-22 | 2. П.2.3.3 | 1 |
24 | 23 | 25 | 22-23 | 2. П.2.3.4 | 1 |
25 | 24 | 26 | 23-24 | 2. П.2.3.5 | 3 |
26 | 25 | 27 | 24-25 | 2. П.2.3.6 | 3 |
27 | 14, 20,26 | 28 | 25-26 | 2. П.3.1 | 4 |
28 | 27 | 29 | 26-27 | 2. П.3.2 | 2 |
29 | 28 | - | 27-28 | 2. П.3.3 | 2 |
3. Викреслюємо сітковий графік виконання робіт по проекту (рис 2.2):
4. Розрахунок параметрів сіткового графіка в табличній формі виконують в такій послідовності:
для кожної роботи вказуємо шифр по подіям і тривалості;
для кожної з робіт розраховуємо ранні строки початку і закінчення за формулами:
TijPП – ранній строк настання роботи;
ThiPП – ранній строк настання попередньої роботи;
thi – тривалість попередньої роботи;
TijPЗ – ранній строк закінчення роботи;
tij – тривалість даної роботи
максимальне значення раннього строку закінчення завершальної роботи визначає критичну тривалість, розробку і реалізацію проекту і приймається рівним пізньому строку закінчення завершальної роботи;
розраховуємо строки пізнього початку і пізнього закінчення кожної з робіт рухаючись по таблиці знизу вверх:
Розраховуємо повний резерв для кожної з робіт.
Повний резерв – це час на який можна збільшити тривалість даної роботи або змістити її початок не змінюючи тривалості критичного шляху.
Табл 2.2. Розрахунок параметрів сіткового графіка в табличній формі
№п/п | к-сть поперед-ніх робіт | шифр роботи по годинах | трива-лість роботи tij, тижні | ранній початок роботи TijРП | раннє закінчен-ня робіт ТijРЗ | пізній початок ТijПП | пізнє закінчен-ня ТijПЗ | загальний резерв RijПЗ | відмітки критич-ного шляху |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
1 | 0 | 1-2 | 11 | 0 | 11 | 0 | 11 | 0 | + |
2 | 1 | 2-4 | 8 | 11 | 19 | 11 | 19 | 0 | + |
3 | 1 | 2-3 | 5 | 1 | 6 | 1 | 6 | 0 | + |
4 | 2 | 4-5 | 2 | 19 | 21 | 19 | 21 | 0 | + |
5 | 1 | 5-6 | 18 | 21 | 39 | 21 | 39 | 0 | + |
6 | 1 | 6-7 | 2 | 39 | 41 | 39 | 41 | 0 | + |
7 | 1 | 7-8 | 2 | 41 | 43 | 41 | 43 | 0 | + |
8 | 1 | 8-9 | 3 | 42 | 45 | 42 | 45 | 0 | + |
9 | 1 | 9-10 | 5 | 45 | 50 | 45 | 50 | 0 | + |
10 | 1 | 10-11 | 13 | 50 | 63 | 50 | 63 | 0 | + |
11 | 1 | 11-12 | 2 | 63 | 65 | 63 | 65 | 0 | + |
12 | 1 | 12-13 | 2 | 87 | 89 | 87 | 89 | 0 | + |
13 | 1 | 13-14 | 3 | 89 | 92 | 89 | 92 | 0 | + |
14 | 1 | 14-25 | 2 | 96 | 98 | 96 | 98 | 0 | + |
15 | 1 | 9-15 | 10 | 45 | 55 | 46 | 56 | 1 | |
16 | 1 | 15-16 | 27 | 55 | 82 | 56 | 83 | 1 | |
17 | 1 | 16-17 | 4 | 82 | 86 | 83 | 87 | 1 | |
18 | 1 | 17-18 | 4 | 74 | 78 | 87 | 91 | 13 | |
19 | 1 | 18-19 | 5 | 78 | 83 | 90 | 95 | 57 | |
20 | 1 | 19-25 | 5 | 83 | 88 | 95 | 100 | 12 | |
21 | 1 | 9-20 | 3 | 45 | 48 | 83 | 86 | 38 | |
22 | 1 | 20-21 | 6 | 48 | 54 | 86 | 92 | 38 | |
23 | 1 | 21-22 | 1 | 54 | 55 | 92 | 93 | 38 | |
24 | 1 | 22-23 | 1 | 55 | 56 | 93 | 94 | 38 | |
25 | 1 | 23-24 | 3 | 56 | 59 | 94 | 97 | 38 | |
26 | 1 | 24-25 | 3 | 59 | 62 | 97 | 100 | 38 | |
27 | 3 | 25-26 | 4 | 100 | 104 | 100 | 104 | 0 | + |
28 | 1 | 26-27 | 2 | 104 | 106 | 104 | 106 | 0 | + |
29 | 1 | 27-28 | 2 | 106 | 108 | 106 | 108 | 0 | + |
Розрахунок параметрів сіткового графіку в табличній формі проводиться по роботам, для яких вказувалися ранні строки початку та закінчення. В подальшому при розрахунку сіткового графіка робіт по проекту в масштабі часу та при графічно-аналітичному способі розрахунку сіткового графіку. Розрахунки сіткового графіку будуть приводитися по подіям для яких будуть вказуватися ранні строки настання та ранні строки закінчення.
Послідовність побудови сіткового графіку в масштабі часу:
Викреслюється вісь часу в тижнях.
Усі роботи зображені в масштабі часу, при цьому початкову подію кожної роботи розміщують у відповідності з її ранніми строками настання. Який розраховується
=maxде, Tрі – ранній строк настання даної події;
Tрh – ранній строк настання попередньої події;
thi – тривалість попередньої роботи.
; =46+10=56 ; =56+27=83 ; =83+4=87 ; =87+4=91 ; =91+5=96 ; =46+3=49 =39+2=41 =49+6=55 =41+2=43 =55+1=56 =43+3=46 =56+1=57 =46+5=51 =57+1=58 =51+13=64 =96+5=101 =64+2=66 =101+4=105