Расчет параметров сетевого графика графическим методом
Рис.3 вычисление параметров непосредственно на сетевом графике
Результаты данных расчетов занесены в таблицу 2:
i,j | t i,j | T pj | Tnj | Rj | Tpi | TpHi,j | Tpoi,j | TnHi,j | Tnoi,j | Rni,j | Rci,j |
0,1 | 7 | 7 | 7 | 0 | 0 | 0 | 7 | 0 | 7 | 0 | 0 |
1,2 | 10 | 17 | 23 | 6 | 7 | 7 | 17 | 13 | 23 | 6 | 0 |
1,3 | 6 | 13 | 13 | 0 | 7 | 7 | 13 | 7 | 13 | 0 | 0 |
2,4 | 3 | 20 | 26 | 6 | 17 | 17 | 20 | 23 | 26 | 6 | 0 |
2,6 | 2 | 19 | 44 | 25 | 17 | 17 | 19 | 42 | 44 | 25 | 0 |
3,4 | 2 | 20 | 26 | 6 | 13 | 13 | 15 | 24 | 26 | 11 | 5 |
3,5 | 16 | 29 | 29 | 0 | 13 | 13 | 29 | 13 | 29 | 0 | 0 |
4,5 | 3 | 29 | 29 | 0 | 20 | 20 | 23 | 26 | 29 | 6 | 6 |
5,7 | 5 | 34 | 34 | 0 | 29 | 29 | 34 | 29 | 34 | 0 | 0 |
5,8 | 4 | 37 | 37 | 0 | 29 | 29 | 33 | 33 | 37 | 4 | 4 |
6.9 | 3 | 47 | 47 | 0 | 19 | 19 | 22 | 44 | 47 | 25 | 25 |
6,10 | 6 | 53 | 53 | 0 | 19 | 19 | 25 | 47 | 53 | 28 | 28 |
7,8 | 3 | 37 | 37 | 0 | 34 | 34 | 37 | 34 | 37 | 0 | 0 |
8,9 | 10 | 47 | 47 | 0 | 37 | 37 | 47 | 37 | 47 | 0 | 0 |
9,10 | 6 | 53 | 53 | 0 | 47 | 47 | 53 | 47 | 53 | 0 | 0 |
Подробности расчетов некоторых из показателей:
TpH i,j = Tpi
Tpo 0,1 = 0+7 = 7; Tpo 1,2 = 7+10 = 17; Tpo 1,3 = 7+6 = 13;
Tpo 2,4 = 17+3 = 20; Tpo 2,6 = 17+2 = 19; Tpo 3,4 = 13+2 = 15;
Tpo 3,5 = 13+16 = 29; Tpo 4,5 = 20+3 =23; Tpo 5,7 = 29+5 = 34;
Tpo 5,8 = 29+4 = 33; Tpo 6,9 = 19+3 = 22; Tpo 6,10 = 19+6 = 25;
Tpo 7,8 = 34+3 = 37; Tpo 8,9 = 37+10 = 47; Tpo 9,10 = 47+6 = 53.
TnH 0,1 = 7 – 7 = 0; TnH 1,2 = 23 – 10 = 13; TnH 1,3 = 13 – 6 = 7;
TnH 2,4 = 26 – 3 = 23; TnH 2,6 = 44 – 2 = 42; TnH 3,4 = 26 – 2 = 24;
TnH 3,5 = 29 – 16 = 13; TnH 4,5 = 29 – 3 = 26; TnH 5,7 = 34 – 5 = 29;
TnH 5,8 = 37 – 4 = 33; TnH 6,9 = 47 – 3 = 44; TnH 6,10 = 53 – 6 = 47;
TnH 7,8 = 37 – 3 = 34; TnH 8,9 = 47 – 10 = 37; TnH 9,10 = 53 – 6 = 47.
Tnoi,j = Tnj
Rn0,1 = 7–0–7 = 0; Rn1,2 = 23–7–10 = 6; Rn1,3 = 13–7–6 = 0;
Rn2,4 = 26–17–3 = 6; Rn2,6 = 44–17–2 = 25; Rn3,4 = 26–13–2 = 11;
Rn3,5 = 29–13–16 = 0; Rn4,5 = 29–20–3 = 6; Rn5,7 = 34–29–5 = 0;
Rn5,8 = 37–29–4 = 4; Rn6,9 = 47–19–3 = 25; Rn6,10 = 53–19–6 = 28;
Rn7,8 = 37–34–3 = 0; Rn8,9 = 47–37–10 = 0; Rn9,10 = 53–47–6 = 0;
Rc 0,1 = 7–0–7 = 0; Rc 1,2 = 17–7–10 = 0; Rc 1,3 = 13–7–6 = 0;
Rc 2,4 = 20–17–3 = 0; Rc 2,6 = 19–17–2 = 0; Rc 3,4 = 20–13–2 = 5;
Rc 3,5 = 29–13–16 = 0; Rc 4,5 = 29–20–3 = 6; Rc 5,7 = 34–29–5 = 0;
Rc 5,8 = 37–29–4 = 4; Rc 6,9 = 47–19–3 = 25; Rc 6,10 = 53–19–6 = 28;
Rc 7,8 = 37–34–3 = 0; Rc 8,9 = 47–37–10 = 0; Rc 9,10 = 53–47–6 = 0;
Определяем продолжительность критического пути (Rj = 0)
t (Lkp) = 7+6+16+3+5+4+3+6+3+10+6 = 66
Расчет параметров сетевого графика табличным методом.
Таблица 3
Код работ | Кол-во предшед. работ | t i,j | TpHi,j | Tpoi,j | TnHi,j | Tnoi,j | Rni,j | Rci,j | Rj | Коды работLkp |
0,1 | 0 | 7 | 0 | 7 | 0 | 7 | 0 | 0 | 0 | 0,1 |
1,2 | 1 | 10 | 7 | 17 | 13 | 23 | 6 | 0 | 6 | |
1,3 | 1 | 6 | 7 | 13 | 7 | 13 | 0 | 0 | 0 | 1,3 |
2,4 | 1 | 3 | 17 | 20 | 23 | 26 | 6 | 0 | 6 | |
2,6 | 1 | 2 | 17 | 19 | 42 | 44 | 25 | 0 | 25 | |
3,4 | 1 | 2 | 13 | 15 | 24 | 26 | 11 | 5 | 6 | |
3,5 | 1 | 16 | 13 | 29 | 13 | 29 | 0 | 0 | 0 | 3,5 |
4,5 | 2 | 3 | 20 | 23 | 26 | 29 | 6 | 6 | 0 | |
5,7 | 2 | 5 | 29 | 34 | 29 | 34 | 0 | 0 | 0 | 5,7 |
5,8 | 2 | 4 | 29 | 33 | 33 | 37 | 4 | 4 | 0 | |
6.9 | 1 | 3 | 19 | 22 | 44 | 47 | 25 | 25 | 0 | |
6,10 | 1 | 6 | 19 | 25 | 47 | 53 | 28 | 28 | 0 | |
7,8 | 1 | 3 | 34 | 37 | 34 | 37 | 0 | 0 | 0 | 7,8 |
8,9 | 2 | 10 | 37 | 47 | 37 | 47 | 0 | 0 | 0 | 8,9 |
9,10 | 2 | 6 | 47 | 53 | 47 | 53 | 0 | 0 | 0 | 9,10 |
Подробности расчетов некоторых показателей:
TpH 0,1 = 0; TpH 1,2 = 0+7 = 7; TpH 1,3 = 0+7 = 7;
TpH 2,4 = 7+10 = 17; TpH 2,6 = 7+10 = 17; TpH 3,4 = 7+6 = 13;
TpH 3,5 = 7+6 = 13; TpH 4,5 = 17+3 = 20; TpH 5,7 = 13+16 = 29;
TpH 5,8 = 13+16 = 29; TpH 6,9 = 17+2 = 19; TpH 6,10 = 17+2 = 19;
TpH 7,8 = 29+5 = 34; TpH 8,9 = 34+3 = 37; TpH 9,10 = 37+10 = 47.
Tpo 0,1 = 0+7 = 7; Tpo 1,2 = 7+10 = 17; Tpo 1,3 = 7+6 = 13;
Tpo 2,4 = 17+3 = 20; Tpo 2,6 = 17+2 = 19; Tpo 3,4 = 13+2 = 15;
Tpo 3,5 = 13+16 = 29; Tpo 4,5 = 20+3 = 23; Tpo 5,7 = 29+5 = 34;
Tpo 5,8 = 29+4 = 33; Tpo 6,9 = 19+3 = 22; Tpo 6,10 = 19+6 = 25;
Tpo 7,8 = 34+3 = 37; Tpo 8,9 = 37+10 = 47; Tpo 9,10 = 47+6 = 53;
Tno 9,10 = 53; Tno 8,9 = 53–6 = 47; Tno 7,8 = 47–10 = 37;
Tno 6,10 = 53; Tno 6,9 = 53–6 = 47; Tno 5,8 = 47–10 = 37;
Tno 5,7 = 37–3 = 34; Tno 4,5 = 33–4 = 29; Tno 3,5 = 33–4 = 29;
Tno 3,4 = 29–3 = 26; Tno 2,6 = 47–3 = 44; Tno 2,4 = 29–3 = 26;
Tno 1,3 = 29–16 = 13; Tno 1,2 = 26–3 = 23; Tno 0,1 = 13–6 = 7;
TnH 0,1 = 7–7 = 0; TnH 1,2 = 23–10 = 13; TnH 1,3 = 13–6 = 7;
TnH 2,4 = 26–3 = 23; TnH 2,6 = 44–2 = 42; TnH 3,4 = 26–2 = 24;
TnH 3,5 = 29–16 = 13; TnH 4,5 = 29–3 = 26; TnH 5,7 = 34–5 = 29;
TnH 5,8 = 37–4 = 33; TnH 6,9 = 47–3 = 44; TnH 6,10 = 53–6 = 47;
TnH 7,8 = 37–3 = 34; TnH 8,9 = 47–10 = 37; TnH 9,10 = 53–6 = 47;
Rn 0,1 = 7–7 = 0; Rn 1,2 = 23–17 = 6; Rn 1,3 = 13–13 = 0;
Rn 2,4 = 26–20 = 6; Rn 2,6 = 44–19 = 25; Rn 3,4 = 26–15 = 11;
Rn 3,5 = 29–29 = 0; Rn 4,5 = 29–23 = 6; Rn 5,7 = 34–34 = 0;
Rn 5,8 = 37–33 = 4; Rn 6,9 = 47–22 = 25; Rn 6,10 = 53–25 = 28;
Rn 7,8 = 37–37 = 0; Rn 8,9 = 47–47 = 0; Rn 9,10 = 53–53 = 0;
R1 = 7–7 = 0; R2 = 23–17 = 6; R3 = 13–13 = 0;
R4 = 26–20 = 6; R5 = 44–19 = 25; R6 = 26–20 = 6;
R7 = 29–29 = 0; R8 = 29–29 = 0; R9 = 34–34 = 0;
R10 = 37–37 = 0; R11 = 47–47 = 0; R12 = 53–53 = 0
R13 = 37–37 = 0; R14 = 47–47 = 0; R15 = 53–53 = 0;
Rc 0,1 = 0–0 = 0; Rc 1,2 = 6–6 = 0; Rc 1,3 = 0–0 = 0;
Rc 2,4 = 6–6 = 0; Rc 2,6 = 25–25 = 0; Rc 3,4 = 11–6 = 5;
Rc 3,5 = 0–0 = 0; Rc 4,5 = 6–0 = 6; Rc 5,7 = 0–0 = 0;
Rc 5,8 = 4–0 = 4; Rc 6.9 = 25–0 = 25; Rc 6,10 = 28–0 = 28;
Rc 7,8 = 0–0 = 0; Rc 8,9 = 0–0 = 0; Rc 9,10 = 0–0 = 0;
Построение карты сетевого проекта
После расчета параметров сетевой график вычерчивается в масштабе времени, т.е. строится карта проекта выполнения работ; в том же масштабе времени строится график загрузки исполнителей. Данный график представлен к рассмотрению в Приложении 1.
Оптимизация сетевого графика по времени
Для оптимизации графика по времени необходимо:
1. Рассчитать продолжительность всех путей
t(0,1,2,6,10) = 7+10+2+6 = 25
t(0,1,2,4,5,8,9,10) =7+10+3+3+4+10+6 = 46
t(0,1,2,6,9,10) = 7+10+2+3+6 = 28
t(0,1,3,4,5,8,9,10) = 7+6+2+3+4+10+6 = 38
tkp(0,1,3,5,7,8,9,10) = 7+6+16+5+3+10+6 = 53
2. Далее определяется коэффициент напряженности выполнения работ, представленный в таблице 4:
i,j | 0,1 | 1,2 | 1,3 | 2,4 | 2,6 | 3,4 | 3,5 | 4,5 | 5,7 | 5,8 | 6,9 | 6,10 | 7,8 | 8,9 | 9,10 |
KH | 1 | 0,76 | 1 | 0,76 | 0,37 | 0,37 | 1 | 0,76 | 1 | 0,76 | 0,5 | 0,39 | 1 | 1 | 1 |
Из расчета видно, что большими резервами обладают работы (2,6) и (3,4). Исходя из этого, процесс оптимизации может идти путем перераспределения ресурсов с этих работ на работы критического пути. Для этого выберем одну работу – (3,4). С данной работы снимаем работников на самую длинную работу критического пути – (3,5).
3. Директивный срок наступления завершающего события Тд = 43 дня, определим вероятность совершения завершающего события:
Рк<0.35, следовательно, необходимо провести оптимизацию сетевого графика по времени.
Оптимизация сетевого графика по времени проводится в такой последовательности:
1. Пересматривается топология сети. Анализ работ сети показал, что работу (1,3) можно разделить на две параллельно выполняемые работы (1,1`), (1.1``) (Рисунок 4).
Рисунок 4. Перестройка топологии сети
1. Определяется объем работ, с которых предполагается перевести исполнителей на работы критического пути.
Q3,4 = 2 * 4 = 8чел/дня
2. Определяется объем работ критического пути до оптимизации
Q3,5 = 16 *2 = 32 чел/дня.
3. Определяется численность исполнителей, которые могут быть переведены с работы (3,4) на работы критического пути:
B3,4пер = 4–8/(2+5) = 4–2 = 2
4. Определяется численность исполнителей после оптимизации
B3,4’ =4 –2 = 2
5. Определяется численность исполнителей после оптимизации на работах критического пути:
B3,5kp = 2+2 = 4
6. Определяется продолжительность работ после оптимизации
t3,4 = 8/2 = 4 t3,5 = 32/4 = 8
7. Определяется продолжительность изменившихся путей после оптимизации:
t(0,1,2,6,10) = 7+10+2+6 = 25
t(0,1,2,6,9,10) = 7+10+2+3+6 = 28
t(0,1,1”,3,4,5,8,9,10) = 7+2+0+4+10+6 = 36
t(0,1,1”,3,4,5,7,8,9,10) = 7+2+0+3+5+3+10+6 = 36
t(0,1,1’,3,4,5,8,9,10) = 7+4+0+4+3+4+10+6 = 38
t(0,1,1’,3,4,5,7,8,9,10) = 7+4+0+4+3=5+3+10+6 = 42
tkp(0,1,2,4,5,7,8,9,10) = 7+10+3+3+5+3+10+6 = 47
Результаты оптимизации сетевого графика занесены в таблицу 5:
Шифр работ до оптимизации | Шифр работ после оптимизации | До оптимизации | После оптимизации | ||
ti,j | Bi,j | ti,j | Bi,j | ||
0,1 | 0,1 | 7 | 10 | 7 | 10 |
1,2 | 1,2 | 10 | 4 | 10 | 4 |
1,3 | 1,1’ | 4 | 2 | ||
1,1” | 2 | 1 | |||
1’,3 | 0 | 0 | |||
1”,3 | 0 | 0 | |||
2,4 | 2,4 | 3 | 2 | 3 | 2 |
2,6 | 2,6 | 2 | 5 | 2 | 5 |
3,4 | 3,4 | 2 | 4 | 4 | 2 |
3,5 | 3,5 | 16 | 2 | 8 | 4 |
4,5 | 4,5 | 3 | 3 | 3 | 3 |
5,7 | 5,7 | 5 | 4 | 5 | 4 |
5,8 | 5,8 | 4 | 3 | 4 | 3 |
6,9 | 6,9 | 3 | 5 | 3 | 5 |
6,10 | 6,10 | 6 | 5 | 6 | 5 |
7,8 | 7,8 | 3 | 3 | 3 | 3 |
8,9 | 8,9 | 10 | 5 | 10 | 5 |
9,10 | 9,10 | 6 | 3 | 6 | 3 |
8. Расчеты параметров оптимизированного сетевого графика во времени табличным методом в таблице 6: